SBF Center

Project data

Location: Central Business District, Singapore

Completion time: June 2017
31 storeys

Requirements

  • 4 lift cores 
  • Curvature of the building 

Customer

Woh Hup Pte Ltd

Customer's benefit

  • Efficiency
  • Flexible designs
  • Quick assembly
  • Protection
Mr. Shawn Tng
Site Manager

We chose PERI because they are the specialists that can help us integrate their design to suit the clients' requirements in a more effective way.

PERI solution

  • Special RCS-P platforms were designed for the corners and special lipped channels for the platforms were fabricated to suit the requirements of the building
  • For the 4 lift cores that join together 15 units of CB 240 & CB 160 Climbing Systems were installed to 3 of the lift cores between the basement 2 and the rooftop
  • 9 further units were applied to the lift core that ends at level 9 - the CB climbing systems support the wall panels with the brackets providing high bearing capacities
  • The Hoisting Platform and Material Lifter allow quick and simple transportation of the PD8 Tableforms