You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

MH8 Contract 02

Project data

Location: Lorong Lada Hitam, Singapore

A 30 m vertical underground shaft for one of the proposed sewers project in Singapore.

Requirements

  • Reduced construction time by casting both separator wall and circular skin wall together which results in the D-shaped single sided wall formwork
  • There is no need for climbing system due to the crane availability on site

Customer

Ed. Züblin AG – Singapore Branch

Customer's benefit

  • Efficient and reliable site support
  • Cost-effective pre-assembly

PERI solution

  • GRV with SRZ Straight Waler to form into a D-shaped single sided wall formwork