Cable-stayed bridge over the Fraser River
Length: 976 m
Longest span: 244 m
Pylon heights: 86 m
Start of works: 2006
Opening for traffic: 2009
Four H-shaped pylons with continually changing cross sections and extremely high wind loads.
Bilfinger Berger Inc., Vancouver
I have already been working with PERI systems for many years and I am convinced that the ACS Climbing System and the VARIO Wall Formwork are the optimum solution. ACS enabled us to reduce the build time. In my opinion PERI offers the best formwork systems in terms of technology.