Condominium at St Thomas Walk

Project data

Location: St Thomas Walk, Singapore

Two blocks (35 & 36 storeys high)
Completion date: 2016

Requirements

  • Lift core
  • Stairs

Customer

Kimly Construction Pte Ltd

Customer's benefit

  • Maximum efficiency
  • Fast, safe and accurate assembly 
  • Minimum of labor
Mr Anthony Ho
Project Manager

PERI systems are well designed and the components made it easy for us to understand and comprehend and be able to explain and disseminate to our formwork workers on site. I must acknowledged that without the PERI system especially the ST 100 we may not be able to achieve our casting of the transfer slab of 3m in height schedule.

PERI solution

  • VARIO GT 24 Wall Formwork together with the RCS Rail Climbing System is used for the casting of lift core and stairs
  • The usage of hydraulics allows the crane independent climbing of wall formwork and platform together in one single operation
  • GRIDFLEX Grid Element Slab Formwork and PERI UP Rosett Flex a cycle time of 8 days for casting of beams and slabs were achieved